NOTIFY "MISS UTILITY" AT 1-800-257-7777
48 HOURS PRIOR TO START OF ANY EXCAVATION.
SEQUENCE OF INSPECTIONS FOR RESIDENTIAL SINGLE-FAMILY AND TOWNHOUSE CONSTRUCTION *
For Inspections call 228-3700
INSPECTION TYPE | PERMIT TYPE | WHEN |
|---|---|---|
1) Footing | Building | Before pouring concrete |
2) Groundwork | Plumbing | Before backgrading |
3) Slab | Building | Before pouring concrete |
4) Foundation Walls | Building | Before pouring concrete walls, or for reinforce CMU walls. |
5) Backfill | Building | After waterproofing or before backfilling. |
6) Rough-in | Plumbing Mechanical Electrical | Before covering work & 1st Gas Test (if applicable) |
7) Braced Wall Nailing | Building | Before Building Wrap or windows installed |
8) Framing | Building | After trade rough-ins (allows insulation) |
9) Insulation | Building | After insulating (allows close-in). |
10) Gas Test | Plumbing | Before concealing gas piping. |
11) Final | Electrical Mechanical Electrical | After work is complete |
12) Final | Building | After trade finals, before Certificate of Occupancy. |
Other Inspections: (Timing depends on needs) | ||
Service | Electrical | After upgrading service box |
Temporary Power | Electrical | Before Virginia Power will |
Concealment Ditch | Electrical | Before backfilling trench |
Fireplace | Building | Fireplace hearth or throat inspections. |
Sewer/Water Service | Plumbing | When tapping mains/before backfill |