 Fiscal Year 2006 Proposed Budget

SECTION F -- INFRASTRUCTURE AND OPERATIONS

ENGINEERING & CAPITAL PROJECTS

PROGRAM MISSION: To provide high quality capital projects through professional planning, survey, design, and construction management services.

The Engineering and Capital Projects Division provides a systematic and thorough approach to the capital improvement program, which is reflected in the consolidation and management of capital projects, engineering and real estate activities in one division. The goals of the Division are to reduce the time between project approval and project completion, fulfill community expectations, and incorporate sound environmental design.

  • Design Section provides professional and technical expertise to prepare preliminary engineering analyses and final designs for County transportation, streetscape and utility system projects. The Survey Unit conducts field surveys and produces base map sheets with topographic information essential to the preparation of plans and designs for public improvement projects. Construction Management unit follows through with management and inspection of all street, bridge and utility construction within the County right-of-way performed by private developers, utility companies and County contractors.
  • Customer Services Section serves as a central reception and processing point for right-of-way, building, plumbing and demolition permit inquiries, fee collections and media reproduction. It also manages the utility underground and utility marking programs.
  • Mapping Center serves as the Countywide base mapping and analysis section providing project tracking and management, cartographic expertise, aerial photo analysis, data maintenance, and digitizing support for all County agencies. This unit also is responsible for Geographic Information System (GIS) network administration and system analysis, database design and administration, and GIS application development.
  • Real Estate/Right-of-Way provides professional real estate services to County agencies to meet the needs for public services and facilities. The section acquires real estate for government facilities and parklands, negotiates and administers leases for County property, and analyzes and processes vacations, easements and rights-of-way for capital improvement projects.
  • Facilities Design and Construction plans, designs and manages the construction and rehabilitation of County facilities, such as recreation centers, libraries, fire stations and administrative buildings.
Engineering & Capital Projects Division
FY 2004
Actual
FY 2005
Adopted
FY 2006
Proposed
% Change:
'05 to '06
Personnel $3,947,057 $4,325,891 $4,388,615 1%
Non-Personnel 849,009 728,578 730,384 -
4,796,066 5,054,469 5,118,999 1%
Intra-County Charges (184,583) (301,396) (319,040) 6%
Total Expenditures 4,611,483 4,753,073 4,799,959 1%
Revenues 895,678 722,748 893,524 24%
Net Tax Support $3,715,805 $4,030,325 $3,906,435 -3%
Authorized FTEs 91.8 92.8 94.8
Funded FTEs 91.8 92.8 94.8

SIGNIFICANT BUDGET HIGHLIGHTS:

  • Personnel increases by 2.0 FTEs and $62,724.  3.0 FTEs were transferred to this Division from the Office of the Director and 1.0 FTE was transferred during FY 2005 from this Division to the Department of Community Planning, Housing and Development.
  • Increase in intra-county charges reflects the higher cost of services to the Utility Fund.
  • Revenue increases primarily due to new projections for erosion and sediment control collections and revenue from leases.

PERFORMANCE MEASURES:

FY 2002 Actual FY 2003 Actual FY 2004 Actual FY 2005 Estimate FY 2006 Estimate FY 2006 Goal
Mission Outcome Measures
Projects designed within schedule and budget 23 24 35 36 42 43
Percent of projects designed within budget N/A N/A 80% 80% 80% 90%
Projects built within schedule and budget 24 37 25 36 60 70
Number of leases negotiated N/A N/A 18 6 9 9
Encroachments/vacations processed N/A N/A 17 20 20 20
Customer Measures
Percent of Engineering walk-in customers rating service satisfactory or better 90% 90% 80% 85% 90% 95%
Percent of GIS work requests meeting customer target dates 75% 78% 75% 79% 80% 80%
Workload Measures
Miles of engineering field surveys completed 30 30 31 32 32 32
Acres of topographic surveys completed 30 30 31 32 32 32
Linear feet of new sidewalk, curb and gutter inspected (public and private) 69,400 70,000 8,260 14,797 83,000 87,000
Building, plumbing and demolition permits reviewed 4,687 4,800 5,235 5,300 5,400 5,100
Public right-of-way permits issued 485 525 630 700 725 750
Number of GIS data layers maintained 26 30 50 70 95 100
Acquisitions:
Number of properties 6 3 1 7 7 7
  • GIS data layers refers to groups of features entered into the database that are meant to be displayed as a group (e.g. buildings, water system, sanitary sewer system). Each system is mapped separately so that multiple combinations of features can be displayed on a map.
  • Several large developer projects were completed in FY 2003. Though some large developer projects are in progress, they will not be complete until FY 2006. Most of the sidewalk and curb and gutter construction occurs in the latter stages of construction.

FUTURE BUDGET CONSIDERATIONS:

  • GIS Mapping Center staff levels have remained static while County-wide demands for services, including work order requests and the creation and maintenance of new data layers, exceed expectations.
  • Arlington is presently investigating the advantages and disadvantages of taking over the state roadways in the County. If successful, the Public Right-of-Way Permit requests will rise significantly which may require additional staff to support the demand.